How to renovate a store: phases of work, permits, building services, fit-out, timing, costs per m² and how to reduce closure days.
Sooner or later every store needs renovating: worn fixtures, outdated lighting, an image no longer in line with the brand, new sales needs. A well-planned store renovation takes a few weeks and pays for itself with more customers and higher receipts; a badly planned one stops the business for months.
In this guide we cover phases, permits, building services, fixtures, timing, costs per m² and how to reduce closure. If you are starting from scratch, read how much it costs to fit out a store instead.
In short: survey and design, any paperwork with the local council, demolition and building work, services, suspended ceilings and floors, fixture installation, cleaning and opening. A light refresh takes 1–2 weeks, a full renovation 4–10 weeks.
1. The phases of the renovation
| 🔢 Phase | 🛠️ What is done | ⏱️ Indicative duration |
|---|---|---|
| 📐Survey and design | Measurements, layout, renderings, bill of quantities | 1–3 weeks |
| 📝Permits | CILA, SCIA or other paperwork if needed | 0–4 weeks |
| 🔨Building work | Demolition, partitions, plastering, floors | 1–4 weeks |
| 🔌Services | Electrics, lighting, air conditioning, data | 1–3 weeks |
| 🪑Fixtures | Workshop production and installation | 3–6 weeks of production, 2–7 days of installation |
| ✅Completion | Cleaning, testing, stocking the store | 2–5 days |
The trick is to have the fixtures made in the workshop while building work and services are being done in the store: that way installation follows straight after and the closure is shorter.
2. Permits and rules
In Italy, for interior work without structural changes a CILA (certified notice of start of works) filed by a qualified technician is often enough; structural changes or changes to the façade usually require a SCIA (certified notice of start of activity) or another permit. If shop windows and signs change, sign permits are also needed (see our guide to store signs). In a condominium building the property manager must be informed. Each municipality has its own rules: it is worth checking them straight away with a technician.
3. Building services
The electrical system must be upgraded for the new lighting, tills and illuminated display cases, with a certificate of conformity. It is the right moment to switch to LED, review the air conditioning and prepare data cabling and sockets where screens and kiosks will go. For lighting, read our guide to store lighting.
4. Custom fixtures
Fixtures are the part customers see and touch: fitted walls, checkout counter, display cases, fitting rooms, tables. If the store already has a good structure, sometimes changing just the fixtures and lighting is enough. See also the retail design trends for 2027.
💬 Need to renovate your store? Send us photos, floor plan and dates: we will propose a work plan and a turnkey quote. Ask for a proposal →
5. How to reduce closure days
- Plan everything first: design approved and materials ordered before closing.
- Parallel production: fixtures are built while the work is going on.
- Work by zones: where possible, part of the store stays open.
- Evening and night shifts for installations in shopping centres.
- A single point of contact coordinating builders, electricians and joiners.
6. Costs per m²
| 🏪 Intervention | 💶 Indicative cost | ⏱️ Timing |
|---|---|---|
| 🖌️Light refresh (paint, lighting, a few fixtures) | €150–350/m² | 1–2 weeks |
| 🔁New fixtures and lighting | €350–700/m² | 2–4 weeks |
| 🏗️Standard full renovation | €700–1,200/m² | 4–8 weeks |
| 🪑Premium full renovation | from €1,250/m² | 6–10 weeks |
Mistakes to avoid
- Starting work without a final design. Variations and delays guaranteed.
- Ordering fixtures once the work is finished. The store stays closed for extra weeks.
- Forgetting permits. Fines and work to redo.
- Too many suppliers without coordination. Each one waits for the other.
- Saving on services. It shows, and you pay for it later.
The most common works and permits
The type of building permit depends on the work. Exact rules vary from municipality to municipality and must always be checked with a qualified technician, but the general scheme in Italy is as follows.
| 🧱 Intervention | 📝 Examples | 📄 Typical permit |
|---|---|---|
| 🖌️Ordinary maintenance | Painting, replacing floors without changes, fixtures | No building permit |
| 🔧Light extraordinary maintenance | Moving non-load-bearing walls, redoing toilets and services | CILA |
| 🏗️Structural work | New openings in load-bearing walls, mezzanines | SCIA or permit, with structural calculations |
| 🔄Change of use | From office or warehouse to store | Dedicated application, planning check |
| 🪧Façade and sign | New shop window, sign, external awnings | Municipal authorisations, sometimes landscape approval |
Depending on the business, there are also the notice of start of commercial activity, health and hygiene requirements for food shops and bars, and fire prevention for larger premises. Starting the paperwork early is the best way not to delay opening.
An example: from former office to a 90 m² store
An entrepreneur buys a former ground-floor office in a building on a shopping street and wants to turn it into a homeware store. The technician checks whether a change of use is possible and prepares the application; meanwhile layout, services and fixtures are designed. The work includes demolishing some partition walls, redoing the electrical system with new lines for lighting and sockets, a new air-conditioning system, a resin floor, a suspended ceiling with integrated lighting, a wider shop window and an accessible toilet.
The building work takes six weeks; in the same period the workshop produces the custom fixtures, which are installed in four days once the work is finished. The total cost, including building work, services, fixtures, sign and design, is roughly €90,000–140,000, i.e. about €1,000–1,550/m². The store opens ten weeks after work starts, thanks to fixture production running in parallel with the site.
How to choose who carries out the work
There are two routes for a renovation. The first is to give the work to several separate firms — builder, electrician, plumber, joiner — coordinating them yourself or through a site manager: you have more control over individual prices, but you need time and expertise to manage the schedule and the overlaps. The second is to rely on a general contractor or a fit-out company that runs the whole site: one contract, one contact, timing and costs agreed in advance. For those with a business to launch and little time for the site, the second option is often the safest.
In both cases it is worth asking for references, checking that the firms are compliant with insurance and safety requirements, and signing a contract with a description of the work, timing, penalties for delays and payments linked to progress.
The most frequent surprises
In old premises surprises are almost inevitable: non-compliant electrical systems to be completely redone, drains in poor condition, damp in the walls, floors hiding level differences, ceilings with materials requiring special disposal procedures. A thorough site visit before the quote, with small test openings at critical points, reduces the risk. It is still wise to keep a margin of 10–15% of the budget for contingencies and a few days in reserve in the schedule.
A typical schedule
| Phase | Indicative duration | What happens |
|---|---|---|
| ▸Survey and design | 2–4 weeks | Measurements, layout, renderings, choice of materials, quotes |
| ▸Paperwork | 2–8 weeks | Filing with the council, waiting for deadlines or authorisations |
| ▸Demolition and building work | 1–4 weeks | Walls, openings, screeds, suspended ceilings |
| ▸Services | 1–3 weeks | Electrics, data, air conditioning, plumbing |
| ▸Finishes | 1–2 weeks | Floors, painting, cladding |
| ▸Fixtures and fit-out | 3–7 days | Installing the fixtures produced in the workshop |
| ▸Cleaning and stock | 2–4 days | Final cleaning, arranging stock, tests |
Many phases overlap: while the council examines the application, the detailed design is completed; while the work is done, the workshop produces the fixtures. Good coordination is what makes it possible to cut the overall time.
Renovating in a shopping centre
In shopping centres renovation follows its own rules. The centre provides a technical manual with requirements for shopfronts, signs, services, materials and fire safety; the design must be approved by management before starting. Work often takes place at night or with the store closed, with scheduled vehicle access and limited space for storing materials. Debris disposal and protection of common areas are also regulated. A firm used to working in shopping centres knows these dynamics and plans the site accordingly, avoiding penalties and delays. Also read our guide to islands and kiosks for shopping centres.
Renovating and saving energy
A renovation is the ideal moment to reduce a store's consumption. LED lighting with control systems, high-efficiency heat-pump air conditioning, insulation of external walls, low-emissivity glass in shop windows and automatic doors or air curtains at the entrance can significantly reduce bills. Some of these measures may qualify for tax incentives or energy-efficiency grants, which change over time: it is worth checking with your accountant and technician before starting work.
Renovating without closing: is it possible?
For many stores, closing for weeks means losing customers and takings. In several cases you can work without closing or closing only for a few days. The method is to divide the store into zones and work on one zone at a time, separating the site from the sales floor with clean, presentable temporary walls; to do the noisiest and dustiest work at night or on closing days; and to prepare everything possible in the workshop, from fixtures to fitted walls, so it can be installed in a few hours. You can also present the renovation to customers as an event, with a window announcing the new store and an opening party at the end of the work.
Not all work allows this: completely redoing services and floors almost always requires closure. In these cases it is best to concentrate it in quieter periods, such as January or August, and prepare everything well in advance.
What to ask before signing
- A quote broken down by item, with quantities and materials described.
- A schedule with start and end dates for each phase.
- Who handles the paperwork and who the site manager is.
- The certificates that will be delivered at the end, such as declarations of conformity for the systems.
- Guarantees on the work and the fixtures, and who intervenes if there are problems.
- Payment terms linked to the progress of the work.
Summary
Renovating a store requires a clear design, paperwork started in good time, a budget with a margin for contingencies and careful coordination between building work, services and fixtures. Producing the custom fixtures while the site is under way and relying on a single point of contact are the choices that most reduce closure days and risks.
Frequently asked questions
Quick answers to the questions we hear most often
Can the work be done in August?
Yes, and it is a common choice to reduce lost takings; but firms and suppliers must be booked well in advance, because many close for the holidays.
Can a rented store be renovated?
Yes, but with the owner's written consent for work that alters the premises; it is also worth clarifying in the lease what will remain with the owner at the end of the tenancy.
Who has to file the building application?
A qualified technician, such as an architect, engineer or surveyor, who signs the design and documentation; the fit-out company or builder provides the technical data needed.
How much does redoing just the electrical system cost?
For a 50–100 m² store, roughly €5,000–15,000, depending on the number of circuits, the distribution board and the planned lighting.
Is it worth redoing the shop window too?
If it is old, poorly insulated or not very secure, yes: a new window improves the image, reduces consumption and increases security, but often requires façade permits.
Do you need to close to install the fixtures?
For fixtures produced in the workshop, a few days of installation are enough, often arranged on closing days or at night.
How much does it cost to renovate a store per m²?
Roughly from €150/m² for a light refresh to over €1,250/m² for a premium full renovation.
How long does it take?
From 1–2 weeks for a light refresh to 4–10 weeks for a full renovation.
Is a permit needed to renovate a store?
It depends on the work: for interior work a CILA is often enough, for structural changes a SCIA is usually needed. This must be checked with a technician.
Do you also supply just the fixtures?
Yes, we can supply custom fixtures only or manage the whole renovation on a turnkey basis.
Do you work throughout Italy?
Yes, we produce in Italy and work throughout Italy and Europe.