Exhibition stand electrical installation: power, switchboard, lighting and certificate of conformity

Exhibition stand electrical installation: power, switchboard, lighting and certificate of conformity

How to design the electrical system of an exhibition stand: power to order, switchboard, LED lighting, sockets, certifications and costs.

The stand’s electrical system is something visitors never see, yet it determines much of the result: without good lighting, products look dull; without sockets in the right place, the LED wall stays black; and without the correct certificates, the show’s technicians may refuse to power the stand until the paperwork is in order. It is also one of the areas where exhibitors make the most mistakes, because it is often decided at the last minute.

In this guide we look at how to calculate the power to order, how the switchboard is built, how to plan lights and sockets, which documents are needed and what it costs. For lights and screens from a communication point of view, also read our guide to LED walls, lighting and audio for stands.

In short: start from the list of loads (lights, screens, fridges, coffee machines, working products), calculate the power and order the connection from the show with a 20–30% margin. The system starts from a switchboard with circuit breakers and residual current devices, is distributed with protected cables and sockets placed where they are needed, and ends with a certificate of conformity signed by a licensed contractor.

1. How much power to order from the show

Electrician connecting the stand’s switchboard

Every exhibition centre sells the power connection as a separate service: the exhibitor chooses the power (in kW) from the technical services catalogue and pays according to the power ordered, not the consumption. Ordering too little means seeing the main breaker trip at peak time; ordering too much means paying for unused power, because at many shows the cost rises significantly for every extra kW.

The calculation is made by adding up the power of all appliances that may run at the same time. Modern LED lights use little power: a stand spotlight draws 15–35 W, an LED strip 10–20 W per metre. Equipment weighs much more: a professional coffee machine 2–3 kW, a refrigerated display 300–600 W, an LED wall 300–800 W per square metre, machinery on display even several kW.

🔌 Load⚡ Typical power📝 Notes
💡Spotlights and LED strips0.5–2 kW per 30–50 m²On all day
📺LED walls and monitors0.3–0.8 kW per m² of screenPeaks with bright images
🧊Fridges and refrigerated displays0.3–0.6 kW eachAlways on, even at night
☕Coffee machine2–3 kWPeaks while heating up
🖥️PCs, tablets, chargers0.2–0.5 kW in totalSockets at the counter and meeting room

A 20–30% margin is added to the total. A 30 m² stand with lights, a monitor and a coffee machine is usually between 3 and 5 kW; a 100 m² stand with an LED wall, kitchen and working products can exceed 15–20 kW and need a three-phase connection.

2. The switchboard and protection devices

Switchboard with residual current devices

The show brings power to a delivery point, usually a floor box or a cable dropping from above. From there the stand’s system begins, always starting with a switchboard. It contains the main switch and a series of circuit breakers and residual current devices that divide the system into circuits: lights, counter sockets, LED wall, kitchen, meeting room. If one appliance fails, only its circuit trips and the rest of the stand stays on.

The switchboard must be placed where staff can reach it but visitors cannot, usually in the storeroom or behind a wall, and must remain accessible throughout the show. It is worth labelling each breaker with its circuit: when something switches off during a demonstration, staff need to understand within seconds where to act.

Many technical regulations also require a switch that cuts power to the whole stand at the end of the day, leaving only night circuits such as fridges and alarms on. This must be planned in the design, otherwise refrigerated displays with products also switch off overnight.

3. LED lighting: how much light and where

LED spotlights on the stand structure

Light is the most powerful tool to make a stand stand out in a hall where everyone competes for attention. The rule is to create contrast: the hall’s general light is even and flat, so the stand needs brighter areas on products, logo and counter. Adjustable spotlights on tracks or trusses let you aim light exactly where it is needed; LED strips built into shelves and under ledges highlight products without glare.

Colour temperature also matters a lot: 3000 K (warm light) for wood, food, fashion and welcoming spaces; 4000 K (neutral light) for technology, industry and white surfaces. For products where colour is decisive, such as fabrics, cosmetics or furniture, you need LEDs with a high colour rendering index (CRI 90 or above), otherwise colours look dull.

In very tall halls the general light is weak: for island or double-deck stands, trusses with lights from above are often hung, but they must be approved by the show as a suspended structure. We cover this in our guide to rigging and suspended structures.

4. Sockets, cables and runs under the platform

Electrical cables under the stand platform

One of the most common sights at a show is the extension cable running across the stand to the monitor, perhaps taped to the carpet. Besides being ugly, it is dangerous and often forbidden. That is why socket positions are decided in the design: at the counter for the till and tablets, under monitors and the LED wall, near working products, in the meeting room for computers and in the storeroom for fridges and the coffee machine.

Cables run inside the walls or under the platform, protected by trunking or corrugated conduit, and reach sockets recessed into the floor or walls. An 8–10 cm raised platform is there precisely for this: it hides the cables, brings power and network to the middle of the stand and makes the floor perfectly level. Floor sockets must have a cover so they do not become a tripping point or a place where liquids are spilled.

Stands with a kitchen, bar or lab sometimes add water and drainage: these also run under the platform and require a design coordinated between electrical and plumbing systems, with safety distances between sockets and sinks.

5. Certificate of conformity and inspections

Multimeter test on a stand socket

In Italy, the stand’s electrical system must be installed by a company licensed under Ministerial Decree 37/08, which issues a certificate of conformity on completion. The document certifies that the system has been installed to professional standards, with certified materials and completed tests. The show usually requires it before opening, and without it may refuse to switch on the supply or ask for a paid inspection by its own technicians.

Before handover the electrician carries out a series of checks: continuity of protective conductors, operation of residual current devices, insulation, correct tightening of terminals, cable temperature under load. The tests are made with specific instruments and the results are recorded. Similar rules apply abroad, with forms and certifications that differ from country to country: that is why it pays to work with a contractor who knows work at shows abroad.

GSR ITALY, the company behind the GECS Group brand, is licensed for electrical work and issues certificates directly, without third parties. This shortens the timing and makes it possible to respond immediately to any requests from the show’s technicians.

6. Installation, testing and safety during the show

Stand lighting test the evening before the show

The electrical system is installed together with the structure: cables are laid before the platform and walls are closed, while spotlights and sockets are connected at the end of build-up. On the last evening a full test is usually carried out with all lights and appliances on, spotlight aiming is checked and it is verified that no circuit is overheating. It is the best moment to correct reflections on graphics or shadows on products.

During the show the system should be used sensibly: no daisy-chained multi-sockets, no heaters or kettles that were not planned, no appliances left on overnight unless necessary. At dismantling, the electrics are disconnected first, before the walls are taken down, so that work is done safely. To see how all the work at the show is organised, read our guide to stand build-up and dismantling.

💬 Not sure how many kW to order from the show or where to place lights and sockets? Send us the floor plan: we design and certify the stand’s electrical system. Talk to a technician →

Special systems: kitchens, machinery and internet

Some stands have needs that go beyond lights and sockets. Food and beverage stands with hot plates, ovens, dishwashers and refrigerated counters draw high power and almost always need a three-phase connection, as well as water and drainage. In these cases the electrical design must be done together with the furniture design: the position of each appliance, the distance from water points and the ventilation of fridge motors decide where cables run and how the switchboard is sized.

Stands with working machinery (tools, robots, packaging lines) need dedicated circuits, protection suited to motors and often a clearly visible emergency stop button. The machine manufacturer must state power, plug type and inrush current, the peak that occurs at start-up: it is the figure most often forgotten and the one that trips the main breaker.

The internet connection should also be planned together with the electrics. The free wifi in the halls is often slow and crowded; for payments, online demos or streaming it is worth ordering a wired line from the show and bringing your own router. The network cable follows the same routes as the power cables under the platform, but kept separate to avoid interference. A simple rule: if a demonstration depends on the internet, always have an offline version on the computer, because on peak days the network can slow down just when the most important clients arrive.

How much does a stand’s electrical system cost

The cost is split into two parts: the connection sold by the show and the internal system installed by the stand contractor. The connection depends on the venue and the power; the internal system depends on how many circuits, lights and sockets are needed.

📏 Item💶 Indicative cost📌 Good to know
🔌Show connection 3–5 kW€300–900Varies greatly between venues
🗄️Stand switchboard€250–800Often rented
💡Spotlights and LED strips€40–120 per light pointReusable for several shows
🧰Sockets and distribution€60–150 per socket pointIncludes cables and trunking
📄Certificate of conformityincluded or €150–300Only from a licensed company

For a 30–40 m² stand with careful lighting, the internal system usually totals €1,500–3,500; for large stands with LED walls, kitchens and working products it easily exceeds €8,000–10,000.

Mistakes to avoid

  1. Ordering the connection late. After the deadlines the show applies significant surcharges.
  2. Underestimating power. Coffee machines and fridges trip the breaker at peak times.
  3. Forgetting night circuits. At night the displays with perishable products switch off too.
  4. Visible extension cables. Ugly, dangerous and often forbidden by the regulations.
  5. Flat light. Spotlights all aimed the same way create no contrast.
  6. Missing documents. Without a certificate of conformity the stand may be left without power.

Electrical checklist

  • Complete list of loads with power and operating hours.
  • Power ordered from the show with a 20–30% margin, before the deadline.
  • Position of the delivery point checked on the hall plan.
  • Switchboard with separate circuits and a night circuit for fridges.
  • Sockets positioned in the design, cables under the platform or inside walls.
  • Spotlights chosen for colour temperature and colour rendering suited to the products.
  • Certificate of conformity ready before opening.

Frequently asked questions

Quick answers to the questions we hear most often

🏛️

Can I bring my own lights and connect them to the stand?

You can bring your own appliances, but connection to the system and certification must be done by a licensed company. The show’s technicians may check non-compliant equipment.

💬

Is a three-phase connection always needed?

No. For most stands up to 6 kW a single-phase connection is enough. Three-phase is needed for high power or for industrial machines in operation.

🔧

Who pays for electricity consumption at the show?

Consumption is usually included in the price of the connection, which is charged according to the power ordered and not the actual kWh.

💬

How far in advance should the connection be ordered?

Each show sets a deadline, usually 4–6 weeks before opening. After that, surcharges apply.

💬

Do you issue the certificate of conformity yourselves?

Yes, we are a licensed company and issue the certificate for the systems we install on stands in Italy.

🖥️

Do you also work on stands designed by others?

Yes, we can carry out just the electrical system or just the build-up, starting from another studio’s design.

Exhibition stand lit with LED lights – GECS Group

Want a stand that is bright, safe and compliant with the show’s rules?

GSR ITALY is licensed for electrical work under Italian Ministerial Decree 37/08: we design, install and certify stand electrics in Italy and abroad, together with structures, graphics and furniture.

Request a free quote →

Request a project

Tell us about the exhibition stand or commercial space you have in mind. We’ll get in touch to discuss the next steps.

DISCUSSION

Comments

Share your thoughts or ask a question about this article.

No comments yet. Be the first.